TGMS: An In-Depth Review of the Whitgift School Hybrid Pitch and Playground Project

Authors:
Dr. Richard Earl, Principal Consultant, TGMS / PSD
Mr. Daniel Ratling, Grounds & Estate Manager, Whitgift School
Dr. James Welsh, Technical Director, White Horse Contractors Limited

BACKGROUND AND OBJECTIVES
Whitgift School is an independent day and boarding school in South Croydon, London with 1550 boys, of which 150 board. The site is an eighteen hectare parkland estate comprising ten hectares of sports facilities and two hectares of gardens and woodland.

Sport is a significant part of life at Whitgift and participation at all ages and abilities is high, with 91% participation at lower-middle school ages. In 2021-22, the school competed in 55 national finals, winning 7 of the core team sports (rugby, football, hockey and cricket) as well as a number of individual titles.

Figure 1. Whitgift School

The school is located in a semi-urban environment and is land-locked with limited space. In order to sustain and develop sports participation and achievement, and to encourage casual play in lunch breaks, the school identified a strategic need to increase the hours of use per week that can be accommodated on the existing limited pitch provision, and also to construct a new playground facility. Two pitches (‘Bigside’ and ‘Puntabout’) were identified for pitch improvement works. Bigside is home to the 1st XV but is also used by other teams down to U13’s, whereas Puntabout is a junior pitch predominantly for younger age groups, but is used by all ages including seniors.

Prior to the pitch improvement works, the pitch surfaces would regularly decline in the winter period resulting in soft, boggy conditions.

Figure 2. Puntabout on 2nd March 2020.

INVESTIGATIVE WORK
TGMS was commissioned by the school to conduct a detailed site investigation and feasibility study, and to assist Daniel Ratling (Grounds & Estate Manager) with the development of a business case for consideration by the senior management team and school Governors. Investigative work included:
• Topographical and geophysical surveys.
• Assessments of pitch orientation and gradients.
• Flood risk assessment.
• Proximity to a groundwater source protection zone (for soakaway suitability).
• BRE Digest 365 soakage tests to inform the design of a surface water drainage system that retains all
water on-site (a likely planning condition).
• The excavation of test pits to characterise the underlying soil and geology to inform pitch and playground design.

It was concluded that the solution would be to construct a new porous polymeric playground in combination with converting Bigside and Puntabout to the first stitched-hybrid grass pitches in a UK independent school. The rationale for selecting a hybrid grass system was:
• Increased hours of use on turf surfaces from 3-6 hours/week to 15-20 hours/week.
• Reduced likelihood of match cancellations.
• The production of high quality & hardwearing grass surfaces

Figure 9. Schematic diagram of the GrassMaster stitched-hybrid system.

DESIGN
TGMS assimilated the results of the investigative work and developed a design solution which included the following:

New playground
• Establishment of a haul route through an established woodland area with root protection requirements.
• Topsoil strip.
• Cut and fill remodeling earthworks.
• Construction of retaining walls.
• Installation of drainage infrastructure.
• Relocation of fencing.
• Construction of the stone foundation.
• Macadam surfacing.
• Polymeric surfacing
• Colour coating.
• Construction of steps from the new playground up to Puntabout.

Puntabout
• Topsoil strip to temporary stockpile.
• Cut & fill re-modelling earthworks.
• Topsoil replacement and grading.
• In-situ stone separation.
• Installation of a geocellular crate soakaway system.
• Installation of a primary land drainage scheme.
• Installation of a fully automatic irrigation scheme.
• Installation of sand bands at 0.5 m spacing.
• Installation of ACO GroundGuard maintenance access track.
• Installation of a ball-stop netting system.
• Application of base fertiliser.
• Placement of 85 mm of sand and 100 mm of rootzone (sand/soil mix).
• Application of pre-seeding fertiliser.
• Seeding.
• Installation of a GrassMaster stitched-hybrid surface reinforcement system.

Bigside
• Rotary cultivation of the topsoil.
• Topsoil re-grading.
• In-situ stone separation.
• Installation of a linear soakaway.
• Installation of a geocellular crate soakaway system.
• Installation of a primary land drainage scheme.
• Installation of a fully automatic irrigation scheme.
• Installation of sand bands at 0.5 m spacing.
• Application of base fertiliser.
• Installation of rootzone carpet.
• Placement of 85 mm of sand and 100 mm of rootzone (sand/soil mix).
• Application of pre-seeding fertiliser.
• Seeding.
• Installation of a GrassMaster stitched-hybrid surface reinforcement system.

TENDER
TGMS conducted a competitive tender process on behalf of the school which resulted in the contract being awarded to White Horse Contractors Limited (part of the S&C Slatter Group).

CONSTRUCTION PHASE

The construction works were project-managed by TGMS in partnership with the school’s Grounds & Estate Manager. The construction team worked efficiently alongside TGMS and the School to deliver the project on time and to budget. Selected photographs of the construction phase are presented below.

Playground

POST-CONSTRUCTION PHASE
A Performance Quality Standard (PQS) assessment was conducted on both pitches on the 26th of October 2021 prior to the proposed first use on Friday 29th October 2021.

The PQS results, presented below, confirmed that both pitches met the performance criteria stipulated in the specification of works:

PQS Results

HANDOVER AND PITCH USE
The pitches were handed over to the school in September 2021 following 7 and 6 ½ weeks grow-in from seeding for Bigside and Puntabout respectively. What a difference two years make.

In autumn / winter 2021-2022 the pitches accommodated ~15 hours of use per week with no cancellations due to rain. There was some natural grass cover loss, but the surface remained flat and stable. From 1st April 2022 until the summer holidays average use increased to more than 30 hours per week.

“I am delighted with the outcome of this project which has created first-class pitches and a new playground ontime and to budget in a working school setting, and has solved a major logistical challenge for the School regarding the provision of sufficient recreational space for our students.”
– Mr. James Stremes, Director of Estates & Facilities

Figure 76. Puntabout on completion.
Figure 79. Bigside in use.

Authors:
Dr. Richard Earl, Principal Consultant, TGMS / PSD
Mr. Daniel Ratling, Grounds & Estate Manager, Whitgift School
Dr. James Welsh, Technical Director, White Horse Contractors Limited

Filter news by: